Client: AO «Valmet Automation»
Work period: September 2019 — April 2020
Project: Commissioning of the biofuel boiler Hybex ® at AO «Mondi SLPK»
View the project description Read moreClient: AO "ILIM Group"
Work period: August, 2019 — October, 2019
Project: : Replacement of wooden sleepers along the edge of the black oil discharge
View the project descriptionClient: AO "Ilim Group"
Work period: November 2018 — June 2019
Project: Development of FEL-2 documentation under the scope of the investment project for the RB No.5 retrofit at Koryazhma
View the project descriptionClient: AO "Ilim Group"
Work period: October 2017 – December 2018
Project: Development of the design and detailed documentation for the re-equipping of recovery boiler RB-1400 No.3 of at the Ust-Ilimsk forest complex
View the project descriptionClient: AO "Ilim Group"
Work period: September 2018 — December 2018
Project: Development of a FEL-3 investment request and design documentation under the scope of the investment project for the RB No.5 retrofit at Koryazhma
View the project descriptionClient: AO "Razrez-Izykhskiy"
Work period: September 2018 — October 2018
Project: DKVR and KE boilers performance-and-commissioning tests using coal at the AO "Razrez Izykhskiy" boiler house
View the project descriptionClient: ZAO "Ekran-Energiya"
Work period: June-August 2018
Project: Feasibility study for the construction of an 8 MW mini-TPP
View the project descriptionClient: PAO "Tyazhstankogidropress"
Work period: June 2017 — January 2018
Project: Development of the basic design and detailed design documentation for the re-equipping of the 20 MW gas boiler house at Tyazhstankogidropress. Equipment supply, installation and commissioning.
View the project descriptionPROJECTS
PRESS CENTER
2022 © ООО "COTES Engineering"